RESIDENTIAL/INDUSTRIAL/COMMERCIAL

The length of track lighting is not the determining factor for determining the number of tracks per branch circuit.

A new FPN added to Sec. 410.151 (B) in the 2008 NEC® eliminates the misconception that Sec. 220.43(B) limits the length of track lighting that you can apply to a branch circuit. Remember, this latter section is found in Part III of Article 220 (Feeder and Service Load Calculations), so the "150VA-per-2 ft.-rule" does not apply to a branch circuit.

The only conditions you must meet are that the connected load on the lighting track must not exceed the rating of the track, and a circuit whose rating exceeds that of the track cannot supply the track.




     Archive

See recent tips in Adobe PDF format

WTF?

You need Acrobat Reader to view these TradeTIPS. So, if you don't have it on your computer, click here to download a free copy.

 


Service Center ElecTech Shop for P&S Stuff Downloads Careers Legrand Companines Site Map Disclaimer French Spanish